Dept. of Trans. PROGRESS Serial No. Contract No. 03-353-13-39 04-251304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-MRN-101-0.1/0.9 Federal Project: ACNH-Q101(17) Progress payment No. 11 Payment period ending: 12-20-03 WEST BAY BUILDERS INC P O BOX 3474 SAN RAFAEL CA 949123474 Escrow No. 02020 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,608,294.86 -8,658.12 2.a. Extra Work 427,140.22 82,964.14 b. Adjustment Comp. 39,525.55 7,543.05 3. Materials on Hand 4. Earned Subject to Retention 4,074,960.63 81,849.07 5. Mobilization 404,484.00 0.00 6. Total Work Completed 4,479,444.63 7. Deductions 8. a.Contract Retentions -203,748.03 -4,092.45 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,275,696.60 77,756.62 10. Reduction Amt to Escrow 11. Payment to Escrow 203,740.00 12. Net Pymt. this Estimate 77,756.62