Dept. of Trans. PROGRESS Serial No. Contract No. 05-110-11-39 04-253404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 10% 04-SCL-880-3.6/5.4 Federal Project: 04-SCL-101-37.9/38.5 ACIM-880-1(56) Progress payment No. 07 Payment period ending: 04-20-05 AMLAND 3168 KNIGHTS BRIDGE RD SAN JOSE CA 95132 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 170,646.30 -6,250.00 2.a. Extra Work 17,519.91 16,094.45 b. Adjustment Comp. 3. Materials on Hand 24,005.49 22,056.99 4. Earned Subject to Retention 212,171.70 31,901.44 5. Mobilization 112,500.00 0.00 6. Total Work Completed 300,666.21 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 324,671.70 31,901.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,901.44