Dept. of Trans. PROGRESS Serial No. Contract No. 10-111-09-20 04-253784 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 70% 04-ALA-680-0.0/R303.0 Federal Project: 04-SCL-680-7.4/9.9 NONE Progress payment No. 12 Payment period ending: 04-20-10 TOP GRADE CONSTRUCTION INC 50 CONTRACTORS STREET LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,113,946.17 558,691.84 2.a. Extra Work 1,301,250.24 21,188.96 b. Adjustment Comp. 763,840.01 86,956.40 3. Materials on Hand 67,292.59 -371.52 4. Earned Subject to Retention 20,246,329.01 666,465.68 5. Mobilization 1,813,000.00 0.00 6. Total Work Completed 21,992,036.42 7. Deductions -13,600.00 -8,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,045,729.01 658,465.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 658,465.68