Dept. of Trans. PROGRESS Serial No. Contract No. 09-202-10-23 04-253794 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 55% 04-ALA-680-M3.3/R6.4 Federal Project: NONE Progress payment No. 11 Payment period ending: 07-20-09 BAY CITIES PAVING AND GRADING INC P O BOX 6227 CONCORD CA 94524 Escrow No. 02417 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,404,075.93 3,208,127.96 2.a. Extra Work 999,323.88 617,793.37 b. Adjustment Comp. -26,829.02 30,192.48 3. Materials on Hand 466,343.74 -515,296.94 4. Earned Subject to Retention 17,842,914.53 3,340,816.87 5. Mobilization 2,800,000.00 140,000.00 6. Total Work Completed 20,176,570.79 7. Deductions 8. a.Contract Retentions -892,145.73 -167,040.85 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,750,768.80 3,313,776.02 10. Reduction Amt to Escrow 11. Payment to Escrow 892,140.00 12. Net Pymt. this Estimate 3,313,776.02