Dept. of Trans. PROGRESS Serial No. Contract No. 10-263-10-34 04-253794 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 04-ALA-680-M3.3/R6.4 Federal Project: NONE Progress payment No. 25 Payment period ending: 09-20-10 BAY CITIES PAVING AND GRADING INC P O BOX 6227 CONCORD CA 94524 Escrow No. 02417 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,327,296.40 48,294.40 2.a. Extra Work 1,870,690.16 51,891.71 b. Adjustment Comp. -454,308.55 0.00 3. Materials on Hand 4. Earned Subject to Retention 31,743,678.01 100,186.11 5. Mobilization 2,800,000.00 0.00 6. Total Work Completed 34,543,678.01 7. Deductions 8. a.Contract Retentions -1,587,183.90 -5,009.30 b. Unsatisfactory Prog. -5,009.31 -5,009.31 c. Reduction after 95% Comp. 9. Total pay to Contractor 32,951,484.80 90,167.50 10. Reduction Amt to Escrow 11. Payment to Escrow 1,587,180.00 12. Net Pymt. this Estimate 90,167.50