Dept. of Trans. PROGRESS Serial No. Contract No. 18-201-11-56 04-2537C4 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 34% Location: Federal Project: 04-SCL-680-M7.6/M9.9 NONE 04-ALA-680-M0.0/M1.9 Progress payment No. 004 Payment period ending: 07-20-18 J J NGUYEN INC 3172 SALEM DR SAN JOSE CA 95127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 712,716.05 184,579.70 2. a. Extra Work 24,581.25 6,191.35 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 737,297.30 190,771.05 5. Mobilization 55,000.00 2,750.00 6. Total Work Completed 792,297.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 792,297.30 193,521.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 193,521.05