Dept. of Trans. PROGRESS Serial No. Contract No. 06-082-15-09 04-253804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 92% 04-NAP-121-R5.0/R5.7 Federal Project: ACST-P121(20) P-P121(20) ACBR-P121(20) Progress payment No. 36 Payment period ending: 03-20-06 C C MYERS INC P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 02060 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,460,357.35 534,812.28 2.a. Extra Work 1,974,256.44 24,725.66 b. Adjustment Comp. 639,200.43 1,532.50 3. Materials on Hand 205,382.24 -105,064.47 4. Earned Subject to Retention 25,279,196.46 456,005.97 5. Mobilization 2,826,000.00 0.00 6. Total Work Completed 27,899,814.22 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -1,263,959.82 -22,800.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 26,831,236.64 423,205.67 10. Reduction Amt to Escrow 11. Payment to Escrow 1,263,950.00 12. Net Pymt. this Estimate 423,205.67