Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-179-10-21 04-253804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-NAP-121-R5.0/R5.7 Federal Project: ACST-P121(20) P-P121(20) ACBR-P121(20) Progress payment No. 57 Payment period ending: 01-14-08 C C MYERS INC P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 02060 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,121,993.77 -76,078.40 2.a. Extra Work 3,234,214.22 10,892.70 b. Adjustment Comp. 796,041.96 0.00 3. Materials on Hand 4. Earned Subject to Retention 28,152,249.95 -65,185.70 5. Mobilization 2,826,000.00 0.00 6. Total Work Completed 30,978,249.95 7. Deductions 8. a.Contract Retentions -1,388,807.10 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 1,388,807.10 0.00 9. Total pay to Contractor 30,978,249.95 -65,185.70 10. Reduction Amt to Escrow -1,388,800.00 0.00 11. Payment to Escrow 1,388,800.00 12. Net Pymt. this Estimate -65,185.70