Dept. of Trans. PROGRESS Serial No. Contract No. 06-167-08-08 04-258714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 30% 04-SOL-680-R1.4/13.1 Federal Project: ACIM-680-2(349) Progress payment No. 03 Payment period ending: 06-20-06 O C JONES AND SONS INC 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 605,109.26 391,285.26 2.a. Extra Work 41,185.92 22,652.26 b. Adjustment Comp. 35,833.00 35,833.00 3. Materials on Hand 4. Earned Subject to Retention 682,128.18 449,770.52 5. Mobilization 302,500.00 302,500.00 6. Total Work Completed 984,628.18 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 984,628.18 752,270.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 752,270.52