Dept. of Trans. PROGRESS Serial No. Contract No. 03-053-11-17 04-263604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 85% 04-CC-4-R8.4/R8.7 Federal Project: NH-P004(121) Progress payment No. 08 Payment period ending: 02-20-03 WATKIN AND BORTOLUSSI INC 77 LARKSPUR STREET SAN RAFAEL CA 949014886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 319,955.30 6,300.00 2.a. Extra Work 1,663.05 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 321,618.35 6,300.00 5. Mobilization 61,750.00 0.00 6. Total Work Completed 383,368.35 7. Deductions 8. a.Contract Retentions -16,080.92 -315.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 367,287.43 5,985.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,985.00