Dept. of Trans. PROGRESS Serial No. Contract No. 10-358-09-56 04-263724 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 100% 04-CC-80-9.5/14.2 Federal Project: NONE Progress payment No. 15 Payment period ending: 12-20-10 GHILOTTI BROS INC 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,055,674.08 783,883.93 2.a. Extra Work 326,260.97 1,836.80 b. Adjustment Comp. 245,883.60 0.00 3. Materials on Hand 823,043.61 -77,200.75 4. Earned Subject to Retention 15,450,862.26 708,519.98 5. Mobilization 2,040,000.00 0.00 6. Total Work Completed 16,667,818.65 7. Deductions -14,400.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. -70,852.00 -70,852.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 17,405,610.26 637,667.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 637,667.98