Dept. of Trans. PROGRESS Serial No. Contract No. 11-355-15-06 04-264064 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 83% 04-MRN-101-18.6/22.3 Federal Project: NONE Progress payment No. 06 Payment period ending: 12-20-11 GHILOTTI BROTHERS/RM HARRIS JV 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,534,349.40 1,236,687.24 2.a. Extra Work 219,704.33 96,017.73 b. Adjustment Comp. -8,764.58 0.00 3. Materials on Hand 270,378.94 77,904.51 4. Earned Subject to Retention 10,015,668.09 1,410,609.48 5. Mobilization 2,249,790.00 0.00 6. Total Work Completed 11,995,079.15 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,265,458.09 1,410,609.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,410,609.48