Dept. of Trans. PROGRESS Serial No. Contract No. 14-080-15-19 04-264074 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 39% 04-MRN-101-23.3/27.6 Federal Project: 04-SON-101-0.0/0.4 NONE Progress payment No. 15 Payment period ending: 03-20-14 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,510,758.79 519,510.58 2.a. Extra Work 893,151.10 115,214.68 b. Adjustment Comp. 14,944.05 0.00 3. Materials on Hand 175,064.13 -65,153.43 4. Earned Subject to Retention 15,593,918.07 569,571.83 5. Mobilization 2,200,000.00 0.00 6. Total Work Completed 17,618,853.94 7. Deductions -3,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,790,918.07 569,571.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 569,571.83