Dept. of Trans. PROGRESS Serial No. Contract No. 15-050-09-55 04-264074 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 76% Location: Federal Project: 04-MRN-101-23.3/27.6 NONE 04-SON-101-0.0/0.4 Progress payment No. 026 Payment period ending: 02-20-15 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,746,902.50 32,404.84 2. a. Extra Work 2,476,900.91 77,206.19 b. Adustment Comp. 360,617.04 0.00 3. Materials on Hand 4. Earned Subject to Retention 23,584,420.45 109,611.03 5. Mobilization 2,200,000.00 0.00 6. Total Work Completed 25,784,420.45 7. Deductions -14,420.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 25,770,000.45 109,611.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 109,611.03