Dept. of Trans. PROGRESS Serial No. Contract No. 16-076-14-51 04-264074 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 90% Location: Federal Project: 04-MRN-101-23.3/27.6 NONE 04-SON-101-0.0/0.4 Progress payment No. 037 Payment period ending: 03-20-16 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,848,496.00 -500.00 2. a. Extra Work 3,187,925.65 282,253.63 b. Adustment Comp. 381,658.80 0.00 3. Materials on Hand 0.00 -281,247.13 4. Earned Subject to Retention 24,418,080.45 506.50 5. Mobilization 2,200,000.00 0.00 6. Total Work Completed 26,618,080.45 7. Deductions -14,420.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,603,660.45 506.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 506.50