Dept. of Trans. PROGRESS Serial No. Contract No. 16-204-10-01 04-264094 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 4% Location: Federal Project: 04-MRN-101-26.5/27.6 NHP-Q101(261) 04-SON-101-0.0/1.9 LU21-L Progress payment No. 005 Payment period ending: 07-20-16 GHILOTTI BROS / RM HARRIS JV 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,225,225.50 1,791,872.79 2. a. Extra Work 266,396.21 266,396.21 b. Adustment Comp. 353,615.00 353,615.00 3. Materials on Hand 143,461.90 -82,149.40 4. Earned Subject to Retention 3,988,698.61 2,329,734.60 5. Mobilization 3,150,000.00 3,150,000.00 6. Total Work Completed 6,995,236.71 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,138,698.61 5,479,734.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,479,734.60