Dept. of Trans. PROGRESS Serial No. Contract No. 16-355-15-22 04-264094 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 23% Location: Federal Project: 04-MRN-101-26.5/27.6 NHP-Q101(261) 04-SON-101-0.0/1.9 LU21-L Progress payment No. 010 Payment period ending: 12-20-16 GHILOTTI BROS / RM HARRIS JV 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,632,250.93 230,329.73 2. a. Extra Work 831,154.12 63,386.77 b. Adustment Comp. 765,567.78 2,320.00 3. Materials on Hand 53,364.01 -125,013.37 4. Earned Subject to Retention 11,282,336.84 171,023.13 5. Mobilization 3,990,000.00 0.00 6. Total Work Completed 15,218,972.83 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,272,336.84 171,023.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 171,023.13