Dept. of Trans. PROGRESS Serial No. Contract No. 17-167-13-44 04-264094 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 29% Location: Federal Project: 04-MRN-101-26.5/27.6 NHP-Q101(261) 04-SON-101-0.0/1.9 LU21-L Progress payment No. 016 Payment period ending: 06-20-17 GHILOTTI BROS / RM HARRIS JV 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,945,720.33 808,530.21 2. a. Extra Work 1,409,754.55 89,217.04 b. Adustment Comp. 1,016,421.78 539.20 3. Materials on Hand 195,861.56 1,489.36 4. Earned Subject to Retention 14,567,758.22 899,775.81 5. Mobilization 3,990,000.00 0.00 6. Total Work Completed 18,361,896.66 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,557,758.22 899,775.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 899,775.81