Dept. of Trans. PROGRESS Serial No. Contract No. 17-268-15-35 04-264094 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 44% Location: Federal Project: 04-MRN-101-26.5/27.6 NHP-Q101(261) 04-SON-101-0.0/1.9 LU21-L Progress payment No. 020 Payment period ending: 09-20-17 GHILOTTI BROS / RM HARRIS JV 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,930,517.74 2,092,210.32 2. a. Extra Work 2,120,139.47 349,082.52 b. Adustment Comp. 1,051,642.96 -2,303.58 3. Materials on Hand 151,103.30 -17,274.88 4. Earned Subject to Retention 20,253,403.47 2,421,714.38 5. Mobilization 3,990,000.00 0.00 6. Total Work Completed 24,092,300.17 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,243,403.47 2,421,714.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,421,714.38