Dept. of Trans. PROGRESS Serial No. Contract No. 18-022-15-05 04-264094 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 60% Location: Federal Project: 04-MRN-101-26.5/27.6 NHP-Q101(261) 04-SON-101-0.0/1.9 LU21-L Progress payment No. 025 Payment period ending: 01-20-18 GHILOTTI BROS / RM HARRIS JV 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,444,592.77 298,961.09 2. a. Extra Work 2,838,328.65 31,592.84 b. Adustment Comp. 1,507,551.79 4,134.94 3. Materials on Hand 100,654.70 0.00 4. Earned Subject to Retention 26,891,127.91 334,688.87 5. Mobilization 4,200,000.00 0.00 6. Total Work Completed 30,990,473.21 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,091,127.91 334,688.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 334,688.87