Dept. of Trans. FINAL Serial No. Contract No. 20-322-08-42 04-264094 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-MRN-101-26.5/27.6 NHP-Q101(261) 04-SON-101-0.0/1.9 LU21-L Progress payment No. 056 Payment period ending: 02-25-20 GHILOTTI BROS / RM HARRIS JV 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 39,080,614.33 0.00 2. a. Extra Work 10,442,382.30 10,561.57 b. Adustment Comp. 5,285,411.78 0.00 3. Materials on Hand 4. Earned Subject to Retention 54,808,408.41 10,561.57 5. Mobilization 4,200,000.00 0.00 6. Total Work Completed 59,008,408.41 7. Deductions -57,071.14 -35,557.24 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 58,951,337.27 -24,995.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -24,995.67