Dept. of Trans. PROGRESS Serial No. Contract No. 22-258-16-17 04-2640F4 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 86% Location: Federal Project: 04-SON-101-3.7/7.2 ACNH-Q101(353) Progress payment No. 036 Payment period ending: 09-20-22 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 67,119,153.66 1,462,010.36 2. a. Extra Work 8,859,178.10 304,282.37 b. Adustment Comp. 1,562,123.01 84,305.89 3. Materials on Hand 365,934.45 58,008.01 4. Earned Subject to Retention 77,906,389.22 1,908,606.63 5. Mobilization 6,150,000.00 0.00 6. Total Work Completed 83,690,454.77 7. Deductions -92,636.38 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 83,963,752.84 1,908,606.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,908,606.63