Dept. of Trans. PROGRESS Serial No. Contract No. 13-165-14-19 04-2640G4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 5% 04-MRN-101-20.5/20.9 Federal Project: NONE Progress payment No. 01 Payment period ending: 06-20-13 GHILOTTI BROTHERS/R M HARRIS JOINT VENTURE 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 107,239.30 107,239.30 2.a. Extra Work 5,235.86 5,235.86 b. Adjustment Comp. 3. Materials on Hand 80,325.00 80,325.00 4. Earned Subject to Retention 192,800.16 192,800.16 5. Mobilization 134,500.00 134,500.00 6. Total Work Completed 246,975.16 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 327,300.16 327,300.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 327,300.16