Dept. of Trans. PROGRESS Serial No. Contract No. 14-149-10-00 04-2640K4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 64% 04-SON-101-3.4/4.1 Federal Project: NONE Progress payment No. 16 Payment period ending: 05-20-14 GHILOTTI-MYERS JV 525 JACOBY STREET SAN RAFAEL, CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,382,004.80 1,348,204.79 2.a. Extra Work 465,642.38 15,449.97 b. Adjustment Comp. 455,163.01 1,750.00 3. Materials on Hand 186,431.72 -262,787.46 4. Earned Subject to Retention 10,489,241.91 1,102,617.30 5. Mobilization 2,083,333.00 104,166.65 6. Total Work Completed 12,386,143.19 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,567,574.91 1,206,783.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,206,783.95