Dept. of Trans. PROGRESS Serial No. Contract No. 14-357-08-44 04-2640K4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 89% 04-SON-101-3.4/4.1 Federal Project: NONE Progress payment No. 23 Payment period ending: 12-20-14 GHILOTTI-MYERS JV 525 JACOBY STREET SAN RAFAEL, CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,333,832.48 604,867.30 2.a. Extra Work 665,050.14 862.50 b. Adjustment Comp. 1,251,069.85 449,610.34 3. Materials on Hand 196,716.75 4,950.00 4. Earned Subject to Retention 16,446,669.22 1,060,290.14 5. Mobilization 2,083,333.00 0.00 6. Total Work Completed 18,333,285.47 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,525,002.22 1,060,290.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,060,290.14