Dept. of Trans. PROGRESS Serial No. Contract No. 15-355-13-34 04-2640U4 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 85% Location: Federal Project: 04-SON-101-0.9/3.6 NONE Progress payment No. 039 Payment period ending: 12-20-15 GHILOTTI - MYERS JV 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,745,327.47 692,546.77 2. a. Extra Work 6,182,451.18 188,710.44 b. Adustment Comp. 1,649,653.87 0.00 3. Materials on Hand 845,605.57 373,934.48 4. Earned Subject to Retention 62,423,038.09 1,255,191.69 5. Mobilization 6,472,000.00 0.00 6. Total Work Completed 68,049,432.52 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 68,885,038.09 1,255,191.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,255,191.69