Dept. of Trans. PROGRESS Serial No. Contract No. 16-172-14-47 04-2640U4 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 86% Location: Federal Project: 04-SON-101-0.9/3.6 NONE Progress payment No. 045 Payment period ending: 06-20-16 GHILOTTI-MYERS,JV 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 57,583,789.35 -6,133.42 2. a. Extra Work 9,092,454.22 126,434.67 b. Adustment Comp. 1,518,828.06 0.00 3. Materials on Hand 54,939.23 -11,965.58 4. Earned Subject to Retention 68,250,010.86 108,335.67 5. Mobilization 6,472,000.00 0.00 6. Total Work Completed 74,667,071.63 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 74,712,010.86 108,335.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 108,335.67