Dept. of Trans. PROGRESS Serial No. Contract No. 16-231-13-23 04-2640U4 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 92% Location: Federal Project: 04-SON-101-0.9/3.6 NONE Progress payment No. 047 Payment period ending: 08-20-16 GHILOTTI-MYERS,JV 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 57,552,163.36 -177,960.32 2. a. Extra Work 9,535,407.67 283,295.94 b. Adustment Comp. 1,718,950.41 0.00 3. Materials on Hand 34,993.23 -10,950.06 4. Earned Subject to Retention 68,841,514.67 94,385.56 5. Mobilization 6,472,000.00 0.00 6. Total Work Completed 75,278,521.44 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 75,303,514.67 94,385.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 94,385.56