Dept. of Trans. PROGRESS Serial No. Contract No. 12-167-14-12 04-264144 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 3% 04-NAP-12-2.8/3.3 Federal Project: 04-SOL-12-0.0/R2.6 ACST-P102(107) P-P102(107) Progress payment No. 05 Payment period ending: 06-20-12 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,914,878.00 1,213,503.00 2.a. Extra Work 12,598.60 6,256.91 b. Adjustment Comp. 150,762.00 0.00 3. Materials on Hand 366,992.48 366,992.48 4. Earned Subject to Retention 2,445,231.08 1,586,752.39 5. Mobilization 1,625,000.00 1,625,000.00 6. Total Work Completed 3,703,238.60 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,070,231.08 3,211,752.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,211,752.39