Dept. of Trans. PROGRESS Serial No. Contract No. 14-085-12-32 04-264144 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 87% 04-NAP-12-2.8/3.3 Federal Project: 04-SOL-12-0.0/R2.6 ACST-P102(107) P-P102(107) Progress payment No. 28 Payment period ending: 03-20-14 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,632,345.88 580,876.00 2.a. Extra Work 2,262,659.27 309,351.98 b. Adjustment Comp. 552,629.89 22,000.00 3. Materials on Hand 357,698.21 -6,757.71 4. Earned Subject to Retention 28,805,333.25 905,470.27 5. Mobilization 3,250,000.00 0.00 6. Total Work Completed 31,697,635.04 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,055,333.25 905,470.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 905,470.27