Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 16-137-16-23 04-264144 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-NAP-12-2.8/3.3 ACST-P102(107) 04-SOL-12-0.0/R2.6 P-P102(107) Progress payment No. 052 Payment period ending: 05-10-16 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,200,418.92 0.00 2. a. Extra Work 4,324,604.77 0.00 b. Adustment Comp. 643,870.32 0.00 3. Materials on Hand 4. Earned Subject to Retention 38,168,894.01 0.00 5. Mobilization 3,250,000.00 0.00 6. Total Work Completed 41,418,894.01 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 41,418,894.01 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00