Dept. of Trans. PROGRESS Serial No. Contract No. 16-112-14-50 04-2641A4 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 5% Location: Federal Project: 04-NAP-12-0.0/3.3 NONE 04-SOL-12-0.0/R2.6 Progress payment No. 006 Payment period ending: 04-20-16 BORTOLUSSI AND WATKIN INC 77 LARKSPUR ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 248,944.12 21,757.12 2. a. Extra Work 3,170.00 3,170.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 252,114.12 24,927.12 5. Mobilization 52,440.00 0.00 6. Total Work Completed 304,554.12 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 304,554.12 24,927.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,927.12