Dept. of Trans. PROGRESS Serial No. Contract No. 17-024-12-29 04-2641A4 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 22% Location: Federal Project: 04-NAP-12-0.0/3.3 NONE 04-SOL-12-0.0/R2.6 Progress payment No. 015 Payment period ending: 01-20-17 BORTOLUSSI AND WATKIN INC 77 LARKSPUR ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 282,590.89 3,620.62 2. a. Extra Work 16,415.34 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 299,006.23 3,620.62 5. Mobilization 55,200.00 0.00 6. Total Work Completed 354,206.23 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 354,206.23 3,620.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,620.62