Dept. of Trans. PROGRESS Serial No. Contract No. 17-331-13-39 04-2641A4 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 41% Location: Federal Project: 04-NAP-12-0.0/3.3 NONE 04-SOL-12-0.0/R2.6 Progress payment No. 025 Payment period ending: 11-20-17 BORTOLUSSI AND WATKIN INC 77 LARKSPUR ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 320,538.43 3,620.62 2. a. Extra Work 35,115.34 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 355,653.77 3,620.62 5. Mobilization 55,200.00 0.00 6. Total Work Completed 410,853.77 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 410,853.77 3,620.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,620.62