Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 23-069-13-20 04-264724 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 13% Location: Federal Project: 04-MRN-101-R20.8/27.1 CML-6204(132) Progress payment No. 009 Payment period ending: 02-20-23 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,735,195.61 384,825.00 2. a. Extra Work 353,795.62 4,921.42 b. Adustment Comp. 9,381.34 0.00 3. Materials on Hand 105,727.00 105,727.00 4. Earned Subject to Retention 8,204,099.57 495,473.42 5. Mobilization 5,358,000.00 0.00 6. Total Work Completed 13,456,372.57 7. Deductions -11,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,551,099.57 495,473.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 495,473.42