Dept. of Trans. PROGRESS Serial No. Contract No. 23-080-17-05 04-264724 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 12% Location: Federal Project: 04-MRN-101-R20.8/27.1 CML-6204(132) Progress payment No. 010 Payment period ending: 03-20-23 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,648,356.70 913,161.09 2. a. Extra Work 444,422.99 90,627.37 b. Adustment Comp. 8,716.15 -665.19 3. Materials on Hand 288,933.20 183,206.20 4. Earned Subject to Retention 9,390,429.04 1,186,329.47 5. Mobilization 5,358,000.00 0.00 6. Total Work Completed 14,459,495.84 7. Deductions -11,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,737,429.04 1,186,329.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,186,329.47