Dept. of Trans. PROGRESS Serial No. Contract No. 25-353-15-53 04-264724 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 67% Location: Federal Project: 04-MRN-101-R20.8/27.1 CML-6204(132) Progress payment No. 043 Payment period ending: 12-20-25 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 64,885,938.25 -2,320,153.00 2. a. Extra Work 14,218,192.43 4,837,529.98 b. Adustment Comp. 292,279.60 0.00 3. Materials on Hand 169,118.30 -440,834.04 4. Earned Subject to Retention 79,565,528.58 2,076,542.94 5. Mobilization 7,144,000.00 0.00 6. Total Work Completed 86,540,410.28 7. Deductions -60,640.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 86,648,888.58 2,076,542.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,076,542.94