Dept. of Trans. PROGRESS Serial No. Contract No. 19-204-10-57 04-270104 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 19% Location: Federal Project: 04-ALA-580-R30.8/R41.5 B1IM-580-1(76) Progress payment No. 004 Payment period ending: 07-20-19 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,124,201.76 2,025,289.19 2. a. Extra Work 25,304.64 25,304.64 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 7,149,506.40 2,050,593.83 5. Mobilization 3,040,000.00 640,000.00 6. Total Work Completed 10,189,506.40 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,189,506.40 2,690,593.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,690,593.83