Dept. of Trans. PROGRESS Serial No. Contract No. 20-113-16-08 04-270104 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 60% Location: Federal Project: 04-ALA-580-R30.8/R41.5 B1IM-580-1(76) Progress payment No. 013 Payment period ending: 04-20-20 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,833,949.64 345,399.44 2. a. Extra Work 782,991.21 92,110.18 b. Adustment Comp. 2,087.25 0.00 3. Materials on Hand 614,962.92 -43,894.15 4. Earned Subject to Retention 18,233,991.02 393,615.47 5. Mobilization 3,200,000.00 0.00 6. Total Work Completed 20,819,028.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,433,991.02 393,615.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 393,615.47