Dept. of Trans. PROGRESS Serial No. Contract No. 20-170-18-11 04-270104 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 68% Location: Federal Project: 04-ALA-580-R30.8/R41.5 B1IM-580-1(76) Progress payment No. 015 Payment period ending: 06-18-20 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,893,551.44 1,601,879.49 2. a. Extra Work 1,075,863.22 253,171.18 b. Adustment Comp. 2,087.25 0.00 3. Materials on Hand 478,784.51 0.00 4. Earned Subject to Retention 23,450,286.42 1,855,050.67 5. Mobilization 3,200,000.00 0.00 6. Total Work Completed 26,171,501.91 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,650,286.42 1,855,050.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,855,050.67