Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 05-144-14-03 04-270304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-MRN-101-0.0/5.7 Federal Project: ACNH-Q101(43) G-Q101(43) Progress payment No. 17 Payment period ending: 04-12-05 DIABLO CONTRACTORS INC 7 CROW CANYON CT SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,872,789.59 0.00 2.a. Extra Work 900,182.98 73,274.72 b. Adjustment Comp. 173,574.77 -1,450.00 3. Materials on Hand 4. Earned Subject to Retention 8,946,547.34 71,824.72 5. Mobilization 800,000.00 0.00 6. Total Work Completed 9,746,547.34 7. Deductions -249,349.12 -249,349.12 8. a.Contract Retentions -443,736.13 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 443,736.13 218,221.21 9. Total pay to Contractor 9,497,198.22 40,696.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 40,696.81