Dept. of Trans. PROGRESS Serial No. Contract No. 10-083-11-50 04-270844 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-SM-1-R43.2/R48.6 Federal Project: 04-SM-280-18.5/27.4 ACST-P307-2(58) 04-SF-280-3.8/4.0 PGH-P307-2(58) Progress payment No. 18 Payment period ending: 03-20-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,724,527.54 400.00 2.a. Extra Work 474,729.24 4,380.54 b. Adjustment Comp. 417,300.06 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,616,556.84 4,780.54 5. Mobilization 1,085,000.00 0.00 6. Total Work Completed 11,701,556.84 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,701,556.84 4,780.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,780.54