Dept. of Trans. PROGRESS Serial No. Contract No. 06-114-10-52 04-270904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 7% 48% 04-SCL-17-6.9/7.2 Federal Project: 04-SCL-101-40.5/51.8 ACST-X085(35) 04-SCL-237-0.8/4.4 PHG-X085(35) Progress payment No. 04 Payment period ending: 04-20-06 CORAL CONSTRUCTION COMPANY P O BOX 347 WILSONVILLE OR 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 142,100.00 69,393.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 36,201.00 -4,525.00 4. Earned Subject to Retention 178,301.00 64,868.00 5. Mobilization 50,000.00 50,000.00 6. Total Work Completed 192,100.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 228,301.00 114,868.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 114,868.00