Dept. of Trans. PROGRESS Serial No. Contract No. 06-263-07-51 04-271604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 11% 04-MRN-101-1.4/7.7 Federal Project: NONE Progress payment No. 07 Payment period ending: 09-20-06 MC GUIRE AND HESTER 9009 RAILROAD AVENUE OAKLAND CA 94603 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 835,185.17 84,254.60 2.a. Extra Work 8,453.51 1,716.97 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 843,638.68 85,971.57 5. Mobilization 150,000.00 7,500.00 6. Total Work Completed 993,638.68 7. Deductions 8. a.Contract Retentions -42,181.93 -4,298.57 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 951,456.75 89,173.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 89,173.00