Dept. of Trans. PROGRESS Serial No. Contract No. 16-140-13-18 04-272054 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 21% Location: Federal Project: 04-SCL-280-7.5/11.5 NHPI-280 1-143 Progress payment No. 002 Payment period ending: 05-20-16 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 104,132.60 95,632.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 104,132.60 95,632.60 5. Mobilization 77,500.00 77,500.00 6. Total Work Completed 181,632.60 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 181,632.60 173,132.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,132.60