Dept. of Trans. PROGRESS Serial No. Contract No. 07-202-09-06 04-272124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 61% 04-CC-4-31.1/40.8 Federal Project: NONE Progress payment No. 08 Payment period ending: 07-20-07 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02282 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,922,175.84 1,298,392.19 2.a. Extra Work 23,343.58 3,391.06 b. Adjustment Comp. -11,011.37 -11,011.37 3. Materials on Hand 4. Earned Subject to Retention 4,934,508.05 1,290,771.88 5. Mobilization 639,000.00 0.00 6. Total Work Completed 5,573,508.05 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -246,725.40 -64,538.59 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,316,782.65 1,216,233.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,216,233.29