Dept. of Trans. PROGRESS Serial No. Contract No. 07-233-08-54 04-272124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 88% 04-CC-4-31.1/40.8 Federal Project: NONE Progress payment No. 09 Payment period ending: 08-20-07 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02282 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,060,580.63 138,404.79 2.a. Extra Work 23,343.58 0.00 b. Adjustment Comp. -11,011.37 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,072,912.84 138,404.79 5. Mobilization 639,000.00 0.00 6. Total Work Completed 5,711,912.84 7. Deductions -12,632.50 -2,632.50 8. a.Contract Retentions -253,645.64 -6,920.24 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,445,634.70 128,852.05 10. Reduction Amt to Escrow 11. Payment to Escrow 160,000.00 12. Net Pymt. this Estimate 128,852.05