Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-341-07-58 04-272124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-CC-4-31.1/40.8 Federal Project: NONE Progress payment No. 11 Payment period ending: 09-04-07 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02282 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,263,925.81 27,030.00 2.a. Extra Work 366,573.57 264,681.72 b. Adjustment Comp. -11,011.37 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,619,488.01 291,711.72 5. Mobilization 639,000.00 0.00 6. Total Work Completed 6,258,488.01 7. Deductions -2,632.50 10,000.00 8. a.Contract Retentions -253,645.64 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 253,645.64 0.00 9. Total pay to Contractor 6,255,855.51 301,711.72 10. Reduction Amt to Escrow -160,000.00 0.00 11. Payment to Escrow 160,000.00 12. Net Pymt. this Estimate 301,711.72