Dept. of Trans. PROGRESS Serial No. Contract No. 08-056-08-33 04-272434 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 26% 04-SON-101-13.6/23.1 Federal Project: NONE Progress payment No. 03 Payment period ending: 02-20-08 MC GUIRE AND HESTER 9009 RAILROAD AVENUE OAKLAND CA 94603 Escrow No. 02334 Total Estimate This Estimate 1. Contract Itms Without Mobil. 305,599.62 9,670.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 72,790.71 72,790.71 4. Earned Subject to Retention 378,390.33 82,460.71 5. Mobilization 118,500.00 0.00 6. Total Work Completed 424,099.62 7. Deductions 8. a.Contract Retentions -37,839.03 -8,246.07 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 459,051.30 74,214.64 10. Reduction Amt to Escrow 11. Payment to Escrow 37,830.00 12. Net Pymt. this Estimate 74,214.64