Dept. of Trans. PROGRESS Serial No. Contract No. 03-199-12-12 04-274204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 30% 22% 04-SM-101-13.4/ .0 Federal Project: ACNH-Q101(29) Progress payment No. 03 Payment period ending: 07-20-03 GORDON N BALL INC 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 02094 Total Estimate This Estimate 1. Contract Itms Without Mobil. 877,537.36 466,382.36 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 877,537.36 466,382.36 5. Mobilization 370,500.00 78,000.00 6. Total Work Completed 1,248,037.36 7. Deductions 8. a.Contract Retentions -76,205.48 -35,089.98 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,171,831.88 509,292.38 10. Reduction Amt to Escrow 11. Payment to Escrow 76,200.00 12. Net Pymt. this Estimate 509,292.38